Nghi Son Oil Refinery

Industrial - Grade I
2013

209 CPTu holes, 5,000m total penetration

Đơn vị ký HĐ: Construction & Environment Consulting Co.

Nhieu Loc - Thi Nghe WWTP

Infrastructure - Special Grade
2020

500m drilling, 780m CPTu, pressuremeter testing, pump testing

Đơn vị ký HĐ: ACCIONA-VINCI Joint Venture

D2400 Water Pipeline (Binh Thai to Dien Bien Phu)

Infrastructure - Special Grade
2018

1,472m drilling, 1,686m CPTu, 711 SPT tests

Đơn vị ký HĐ: Intec International Technical Consulting

HCMC Metro Line 4

Transportation - Grade I
2010

19 CPTu holes, 540m total penetration

Đơn vị ký HĐ: HCMC Survey & Construction Co.

Pháp Vân - Cầu Giẽ Highway Expansion

Transportation - Grade I
2011

43 CPTu holes, 645m penetration on 30km route

Đơn vị ký HĐ: Fukken & Minami Consulting

Lach Huyen Port Infrastructure

Infrastructure - Grade I
2013

CPTu 180m, vane shear 80m with 40 test points

Đơn vị ký HĐ: Fukken & Minami Consulting

Gemalink Container Terminal

Transportation - Grade I
2010

11 CPTu holes, 330m penetration, 33 dissipation tests

Đơn vị ký HĐ: Vina Mekong Construction Consulting

Hiep Phuoc Container Port

Transportation - Grade I
2010

895m drilling, 11 CPTu holes, 13 vane shear holes

Đơn vị ký HĐ: GRUP MARITIM TCB S.L (Spain)

Nhon Trach 2 Thermal Power Plant

Industrial - Grade I
2009

CPTu 100m, 15 dissipation tests, 8 plate load tests

Đơn vị ký HĐ: Fecon Foundation Engineering

Long Phu 1 Thermal Power Plant

Industrial - Grade I
2012

24 CPTu holes, 600m penetration, 8 plate load tests

Đơn vị ký HĐ: Fecon Foundation Institute

Laguna Resort Hue

Civil - Grade I
2008

1,500m drilling, 2,000m geophysics, 750 soil samples

Đơn vị ký HĐ: Laguna Vietnam Co., Ltd

Banyan Tree Resort Hue

Civil - Grade II
2011

360m drilling, 234 soil samples, 18 CBR and load tests

Đơn vị ký HĐ: Laguna Vietnam Co., Ltd

Dong Nai Waterfront City

Civil - Grade I
2010

367ha land + 128ha underwater topographic mapping

Đơn vị ký HĐ: Dong Nai Waterfront City LLC

Binh Dien Commercial Center

Civil - Grade I
2010

860m drilling, CPTu 120m, 50 vane shear points

Đơn vị ký HĐ: PPM Global Ltd (Malaysia)

Binh Dai Wind Power

Industrial - Grade I
2020

14 CPT holes, 840m penetration depth 60m each

Đơn vị ký HĐ: Power China Huadong Engineering

HBRE Chu Prong Wind Farm

Industrial - Grade I
2021

10 CPT holes, 300m penetration

Đơn vị ký HĐ: Powerchina Zhongnan Engineering (Thailand)

BIM 18NX Solar Power (75MW)

Industrial - Grade I
2020

60 CPT holes, 300m total penetration

Đơn vị ký HĐ: BIM

Dak N'Drung Wind Farm

Industrial - Grade I
2023

400m drilling, geophysics, hydrology assessment

Đơn vị ký HĐ: Hung Thinh Construction Co.

Crown Long An Factory

Industrial - Grade I
2022

900m drilling, 450 SPT, 1:500 topographic mapping

Đơn vị ký HĐ: Crown Saigon JV Co., Ltd

Crown Binh Duong Factory

Industrial - Grade I
2022

900m drilling, full lab testing, topographic survey

Đơn vị ký HĐ: Crown Saigon JV Co., Ltd

LPG YHP Cold Storage, Quang Ninh

Industrial
2023

622m drilling, 73.6m CPTu, seismic testing, cyclic triaxial

Đơn vị ký HĐ: TTCL Vietnam

Binh Loi Bridge (pile repair)

Transportation - Grade I
2009-2010

Cement grouting for bored pile defect repair, 3D ultrasonic

Đơn vị ký HĐ: Cienco 6

Sonadezi Building (20 floors)

Civil - Grade I
2009-2010

Settlement monitoring 10 cycles, tilt monitoring 4 cycles

Đơn vị ký HĐ: Bien Hoa IZ Development Co.

Sai Gon Pearl - Topaz Tower (33 floors)

Civil - Special Grade
2007

16 settlement points, 10 monitoring cycles

Đơn vị ký HĐ: Song Da 207 JSC